POPUP
OPEN
상단 팝업 이전
상단 팝업 다음
Do not open this pop-up today.
POPUP
CLOSE
Home
Sitemap
Contact us
Korean
중이온가속기건설구축사업단
mainmenu
About RAON
Project Progress
Organization Chart
Contact Us
About Project
Heavy Ion Accelerator Construction Project
Project Schedule
Project Achievements
Status of Partnerships
Project Mascot
Heavy-ion accelerator RAON
Rare isotopes
Heavy-ion accelerator
Features of RAON
Applied R&D Areas
News Center
Notice
News
Job Opportunities
Gallery
Photo Gallery
Video Gallery
Promotional materials
Study of the fundamental properties of exotic nuclei & the origin of heavy elements in the Universe
About Project
Heavy Ion Accelerator Construction Project
Project Schedule
Project Achievements
Status of Partnerships
Project Mascot
Project Schedule
About Project
Project Schedule
Print Page
System Installation Schedule
'15.12 - ECR-IS beam & SOL beam (SI beam)
'16.12 - RFQ beam
'16.12 - SCL demo beam
'19.05 - SCL installation
'20.10 - ISOL Commissioning
'20.12 - 18.5MeV/u SI beam
'21.01 - D-1 Experiment
'21.09 - 18.5MeV/u RI beam
'21.10 - IF Commissioning
'21.12 - SCL2
Facility Construction Schedule
'15.12 - Completion of basic design
'17.02 - Beginning of priority construction
'17.06 - Completion of detail design
'17.09 - Beginning of construction
'18.10 - Approval for the use of the radiation generator
'18.12 - Supply of utilities
'20.10 - 154kV Power Supply
'20.12 - Completion of construction
'21.04 - Building Permit
'21.12 - Completion of inspection of the radiation generator